In a demonstration of exceeding client’s expectation, Etimaad finished work at the Uch plant two days ahead of schedule with zero lost time injury. During the turnaround, Etimaad performed cleaning of vessels and heat exchangers maintenance work of all rotary equipment, electrical motors, and calibration of equipment at the gas treating plant, dehydration units, water treatment plant and utilities.
A team of 365 skilled manpower, were deployed to perform this activity 60 Km from Dera Murad Jamali. Whole activity was concluded in 14 days and the plant was handed over to Oil and Gas Development Company Limited (OGDCL), owners and operators of the Uch gas field.
OGDCL appreciated Etimaad’s work in a appreciation letter received from client after successful completion of annual shutdown,” We confirm that M/s Etimaad Engineering (Pvt.) Limited has successfully carried out the Annual Outage 2009 from November 1 to 14, 2009, well ahead of planned date of completion of the Uch Gas Processing Plant, Dera Bugti, while maintaining the Quality and Safety”. |